Formwork Design & Installation
Formwork Design & Installation
Steel Rebar Installation
Top Slab - Travelling Falsework
Top Slab - Travelling Falsework
Top Slab formwork mounted on a travelling falsework fixed on rail.
Hydraulically operated travelling formwork system enabled a 30m long, double box, 8 day pour cycle. The formwork was struck, moved and re-positioned in 1 hour.
Top Slab formwork mounted on a travelling falsework fixed on rail.
Hydraulically operated travelling formwork system enabled a 30m long, double box, 8 day pour cycle. The formwork was struck, moved and re-positioned in 1 hour.
Project - 2014-2019
Project - 2014-2019
Project - 2014-2019
Steel fixing in close and strong partnership with third party company.
-
Cutting bending & fixing of 40,000 tons of rebar (10mm Ø to 40mm Ø)
-
Installation of 80,000 couplers
-
Installation of 170 km of Glass Fiber Reinforced Polymer (G.F.R.P.)
Our world, the earth, has been given to us as a gift with limited resources; Therefore all MCS construction actors are committed to a sustainable development and operating practices through the responsible management of energy use, water and waste, emissions, transportation, and procurement.
Beyond the mandatory law and the regulatory compliances, MCS construction promotes the reduction of raw material
Introduction of system platforms and formworks for concrete works to reduce the wastage of timbers


We encourage the procurement of precast structures (instead of on‐site fabrication) to reduce wastage of cements, rebars and timbers
MCS Construction optimizes through digital technologies the resources and bring to the client more control and less risk