Formwork Design & Installation
Formwork Design & Installation
Steel Rebar Installation
Top Slab - Travelling Falsework
Top Slab - Travelling Falsework
Top Slab formwork mounted o​n a travelling falsework fixed on rail.
​
Hydraulically operated travelling formwork system enabled a 30m long, double box, 8 day pour cycle. The formwork was struck, moved and re-positioned in 1 hour.
Top Slab formwork mounted o​n a travelling falsework fixed on rail.
​
Hydraulically operated travelling formwork system enabled a 30m long, double box, 8 day pour cycle. The formwork was struck, moved and re-positioned in 1 hour.
Project - 2014-2019
Project - 2014-2019
Project - 2014-2019
Steel fixing in close and strong partnership with​ third party company.
-
Cutting bending & fixing of 40,000 tons of rebar (10mm Ø to 40mm Ø)
-
Installation of 80,000 couplers
-
Installation of 170 km of Glass Fiber Reinforced Polymer (G.F.R.P.)
Shaft Excavation


Excavation with multiple material types such as reclamation fill, marine deposit and alluvium.
​
We have experience to manage large fleet of excavator, telescopic boom, dump truck, dozer.

Material Transportation and Mixing


Surcharge installation & removal​, material screening, concrete block breaking & crushing to size small block
Our team has the experience to manage the material transportation in a cost-effective way.


Backfill
Backfill in restricted space with the use of telescopic equipment


