Steel Rebar Installation
Top Slab - Travelling Falsework
Top Slab - Travelling Falsework
Top Slab formwork mounted on a travelling falsework fixed on rail.
Hydraulically operated travelling formwork system enabled a 30m long, double box, 8 day pour cycle. The formwork was struck, moved and re-positioned in 1 hour.
Top Slab formwork mounted on a travelling falsework fixed on rail.
Hydraulically operated travelling formwork system enabled a 30m long, double box, 8 day pour cycle. The formwork was struck, moved and re-positioned in 1 hour.
Project - 2014-2019
Project - 2014-2019
Project - 2014-2019
Steel fixing in close and strong partnership with third party company.
-
Cutting bending & fixing of 40,000 tons of rebar (10mm Ø to 40mm Ø)
-
Installation of 80,000 couplers
-
Installation of 170 km of Glass Fiber Reinforced Polymer (G.F.R.P.)
Temporary Steel Structure Design & Installation
Shoring Towers, Propping, Travelers
Assembly, installation & removal of temporary shoring towers, propping, access portals and various temporary structure.
We have an experienced team, competent in safe lifting, assembly and installation of most temporary structures.