Formwork Design & Installation
Formwork Design & Installation
Steel Rebar Installation
Top Slab - Travelling Falsework
Top Slab - Travelling Falsework
Top Slab formwork mounted on a travelling falsework fixed on rail.
Hydraulically operated travelling formwork system enabled a 30m long, double box, 8 day pour cycle. The formwork was struck, moved and re-positioned in 1 hour.
Top Slab formwork mounted on a travelling falsework fixed on rail.
Hydraulically operated travelling formwork system enabled a 30m long, double box, 8 day pour cycle. The formwork was struck, moved and re-positioned in 1 hour.
Project - 2014-2019
Project - 2014-2019
Project - 2014-2019
Steel fixing in close and strong partnership with third party company.
-
Cutting bending & fixing of 40,000 tons of rebar (10mm Ø to 40mm Ø)
-
Installation of 80,000 couplers
-
Installation of 170 km of Glass Fiber Reinforced Polymer (G.F.R.P.)
People who come from different backgrounds add new experiences, talent, and skills into MCS Construction; all of which improve our company performance. By bouncing ideas off each other, our diverse team generates more creative, innovative ideas. Skills diversity also comes into play here. Good diversity management is key to future MCS Construction business success.
Health and Safety
This is our Top Priority and a shared commitment from MCS Construction management, right to our frontline colleagues. Through the visible Safety Leadership of our managers and supervisors, strong involvement of our frontline workers, and the early anticipation of our works to identify and eliminate H&S risks, we strive to achieve our ultimate goal of zero accidents. With the allocation of adequate resources, a culture of transparently sharing opportunities for improvement and the full commitment of each individual from management to frontline in decision-making, we enhance and continually improve our H&S performance.
Promote Sustainable Careers